Answer: 8 days
Explanation:
So, A and C together will do the work in 8 days.
Explanation:
| (A + B + C)'s 1 day's work = | 1 | ; |
| 6 |
| (A + B)'s 1 day's work = | 1 | ; |
| 8 |
| (B + C)'s 1 day's work = | 1 | . |
| 12 |
| |||||||||||||||
| |||||||||||||||
| |||||||||||||||
|